Baker Hughes wins major LNG turbomachinery order

          March 4, 2022

            Baker Hughes will supply gas turbines and centrifugal compressors to support the expansion of the Pluto LNG onshore processing facility in Western Australia.

            The construction of Pluto LNG’s second train (Pluto Train 2) builds on Baker Hughes’ existing technology supply for Pluto LNG’s first train, which has been in operation since 2012, and further expands Baker Hughes’ global turbomachinery fleet in LNG operations. The US$12 billion LNG project is targeted to come online in 2026.

            Pluto Train 2, which is operated by Woodside, has an expected capacity of approximately 5 million tons per annum (mtpa). Pluto Train 2 will process natural gas from the nearby offshore Scarborough field, which contains only around 0.1% carbon dioxide. This makes it an attractive option for Woodside’s major LNG customers seeking reliable, affordable and lower-carbon energy to meet demand and support their countries’ decarbonization goals, according to Baker Hughes.

            Baker Hughes’ scope of supply includes six LM6000PF+ aeroderivative gas turbines and 14 centrifugal compressors for the main refrigerant train, as well as one gas turbine generator in addition to the existing Train 1 power system.

            “This latest order builds on our longstanding relationship with Woodside dating back to 1989, when we first started partnering in pioneering LNG solutions for natural gas supply,” said Rod Christie, executive vice president of Turbomachinery & Process Solutions at Baker Hughes. “Our state-of-the-art technology combined with Woodside’s commitment to supplying lower carbon intensity liquefied natural gas shows how we can responsibly provide secure energy together. Pluto Train 2 will be critical for the energy transition, supporting the strong demand for natural gas and the need for increasingly efficient, safe and reliable LNG operations.”

            Packaging of the turbine/compressor train, manufacturing of compressors and testing of the trains will take place at Baker Hughes’ facilities in Florence and Massa, Italy.

            Pluto LNG is an onshore LNG processing facility located near Karratha in the northwest of Western Australia. First cargo from the single-train facility was delivered in 2012.

            Expansion of Pluto LNG will include the construction of Pluto Train 2, associated domestic gas processing facilities, supporting infrastructure and modifications to Pluto Train 1 to allow it to process Scarborough gas. Bechtel has been selected as the EPC contractor for Pluto Train 2 and integration into existing Pluto LNG facilities.


          主站蜘蛛池模板: 中文字幕AV无码一区二区三区| 国产免费一区二区三区不卡| 国产亚洲一区二区精品| 欧美亚洲精品一区二区| 成人无码AV一区二区| 夜精品a一区二区三区| 日本免费一区二区在线观看| 色老板在线视频一区二区| 日韩美女在线观看一区| 竹菊影视欧美日韩一区二区三区四区五区 | 国产高清视频一区三区| 国产一区二区三区高清视频| 在线不卡一区二区三区日韩| 亚洲丰满熟女一区二区哦| 日韩精品一区二区三区中文| 成人精品视频一区二区三区不卡 | 午夜肉伦伦影院久久精品免费看国产一区二区三区 | 99在线精品一区二区三区| 日韩人妻精品无码一区二区三区| 丰满少妇内射一区| 狠狠色婷婷久久一区二区三区| 日本精品一区二区三区在线视频| 亚洲AV无码一区二区三区性色 | 激情久久av一区av二区av三区| 人妻精品无码一区二区三区| 亚洲综合av一区二区三区 | 爆乳熟妇一区二区三区霸乳| 精品人妻一区二区三区四区| 国产aⅴ一区二区| 一区二区三区四区电影视频在线观看 | 中文字幕日韩人妻不卡一区| 精品伦精品一区二区三区视频| 丰满岳妇乱一区二区三区| 好湿好大硬得深一点动态图91精品福利一区二区 | 免费萌白酱国产一区二区三区| 成人国产一区二区三区| 无码精品人妻一区二区三区中| 成人免费视频一区二区| 国产高清精品一区| 久久精品国产一区二区三| 精品深夜AV无码一区二区老年|